This was a ground remediation project to remove hazardous soils from site to a specialist tip where in some areas excavations were down to a depth of 2.5m.
The project required the transport and removal of up to 40 loads a day of material off site.
In tandem with the muck away operations we were required to import suitable material in order to re-establish the site back to the correct level. Utilising our in house substantial vehicle fleet, we were able to minimise vehicle movements to site.
Throughout the process, Amiante STR maintained a watching brief, to further enhance best working practices and to allow the statutory compliance to be of the highest possible standards.
A further element to the project throughout the excavation process entailed the breakup and crushing of concrete obstructions found. This material was re used on site further minimising vehicle movements
- Excavation and safe disposal of contaminated soils
- Import of suitable fill
- Exposing concrete obstructions
- Crushing concrete material and provide a working platform for future works