Former Allders Department Store

Amiante STR have recently completed a major licensed asbestos removal project to the former Allder’s department store in Camberley, Surrey, completing works eight weeks ahead of the planned thirty week programme.

Scope of Works

The project involved:

  • Removal of approximately 1,900m² of non-asbestos ceiling tiles and ceiling grid per floor
  • Removal of non-asbestos partition walls throughout under full asbestos conditions
  • Removal of asbestos-containing sprayed coating (overspray) from ceiling soffits
  • Removal of sprayed coating from structural beams and columns across all 3no floors
  • Construction of multiple asbestos enclosures to all floors.
  • Removal of all asbestos and correct disposal of generated waste via an enclosed skip which was delivered to a licensed land fill site.
  • Personal monitoring of operatives inside and outside of the enclosure to confirm control measures to be adequate.
  • Havs Monitoring due to the requirement of utilising reciprocating saws to cut out pipework.

The sprayed coating was confirmed to contain Amosite (brown asbestos), classified as asbestos thermal insulation. Due to the high-risk nature of this material, all works were carried out under fully controlled conditions in accordance with regulatory requirements.

Controlled Works & Methodology

The project required:

  • One enclosure on the 2nd floor
  • One enclosure on the 1st floor
  • Two enclosures on the ground floor

A range of specialist removal techniques were utilised, including:

  • Controlled wet stripping using the injection wetting method
  • Aqua blasting via the Torbo wet blast system

Given the scale of the enclosures and the legal requirements for adequate air management, careful planning and engineering controls were critical to maintaining safe working conditions.

Air Management & Independent Monitoring

With other contractors, including Collard Group, operating on site during the asbestos removal works, stringent air monitoring protocols were implemented.

An independent UKAS-accredited analyst carried out:

  • Background air monitoring
  • Leak testing throughout the project
  • Personal monitoring

This ensured enclosure integrity was maintained at all times and demonstrated full compliance with regulatory standards.

HSE Audit

During the works, an inspector from the Health and Safety Executive (HSE) conducted an unannounced site audit. The inspector commended the quality of the RAMS documentation and acknowledged that all associated risks had been thoroughly identified and appropriately controlled.

This project highlights Amiante’s ability to deliver technically demanding asbestos removal schemes safely, compliantly, and ahead of programme — even within complex, multi-contractor environments.

Key Details

Location

Obelisk Road, Camberley, Surrey, GU15 3SD

Client

Surrey Heath Borough Council

Project Size

3no floors of approximately 1900m2 per floor

Value

£1,600,000

Duration

30no weeks programmed, completed in 22no weeks

Key Challenges

Working in close proximity of other contractors
Working at height over 3m
Obtaining air flow for the full 1900m2 per floor

Client Feedback

“‘I thought I would drop you a quick message to say many thanks for the presentation today which was well received by all. Despite attending many ACM training / awareness courses over the years, I am always surprised that there is more to learn about this very dangerous material. With the fantastic number of virtual attendances from SHBC just demonstrates that when people hear the word ‘asbestos’ ears prick-up and there is an eagerness to understand more about how it impacts our everyday lives, whether it is in the work environment or at home.’ – Oander Ltd ‘ “

Services Provided

Asbestos RemovalsAsbestos ServicesPigeon Guano RemovalServices