Deepcut Barracks, Camberley

Amiante STR were contracted to work alongside Collard’s to help the completion of the project. These works included the demolition of existing structures and ground remediation to make way for the development of a new housing estate.

The project posed some significant challenges in regard of previous uses down through the years.

A number of processes were applied to the material found on site to minimise both the need for vehicle movement, and reducing the financial impact to the project.

A number of live services, both buried and overhead were identified during the pre-demolition audit. This pre planned activity allowed to site team to plan and negate the impact of these services on the program.

  • Removal of asbestos both licenced and non-licenced products. Site wide clearance of fly-tipped COSHH waste and asbestos.
  • Segregation/Screening of site hazardous materials, as identified with the clients 3rd party investigations and reports. Aim to declassify various waste streams
  • Testing of all materials on site
  • Screening of materials to reduce muck away costs to the client.

Key Details

Location

Deepcut Barracks, Camberley

Client

Bewley Homes

Project Size

24677sqm

Contract Value

£85,500.00

Duration

12 weeks

Key Challenges

  • • Asbestos / hidden asbestos
  • • Working in the vicinity of biological hazards
  • • Live services including gas, electricity (overhead and underground) and water
  • • Obtaining Network Rail permits to work and approval of all site documents

Reference Details

Bryan Dart

Bryan Dart

Operations Manager