Royal Holloway College

Amiante worked hard to complete all asbestos removal works to a very strict deadline. To ensure the works were completed on time and to the highest standard we increased supervision and operatives.

This project involved the removal of:

Asbestos containing vinyl floor tiles and bitumen throughout the ground floor of all properties. These works were carried out under semi-controlled conditions.

The asbestos containing floor tiles were removed using a big mutt tile lifter, the Bitumen was then removed using a Blastrac floor grinder fitted with a dust extractor.

Asbestos containing textured coating applied to plasterboard ceilings throughout the properties, these works were carried out under controlled conditions and notifying the HSE by way of an NNLW.

The plasterboard ceiling was removed with the Asbestos textured coating still attached.

Asbestos insulation Board boxings in each of the properties. These works were carried out under fully controlled conditions and notifying the HSE by way of ASB5.

Due to works being carried out next to a residential Estate, Collard demolition erected HERAS fencing and secured to site making if safe for the public and all worker involved in the project.

Key Details

Location

1 - 7 Highfields Close, Egham, TW20 0EX

Client

R Collard

Project Size

7no properties
700sqm of asbestos containing textured coatings
350sqm of asbestos containing floor tiles and bitumen
70sqm of asbestos insulation board

Contract Value

£55,000.00

Duration

6no weeks